Kitchen RemodelTimeline.

What happens in each phase, why countertops leave a gap, and what usually causes delays.

The Construction Is Only Part Of The Timeline

When people ask how long a kitchen remodel takes, they usually mean the weeks the kitchen is torn up. But a kitchen remodel really has two timelines: the planning and ordering that happen before demolition, and the construction that happens after. The first one is where most delays start, and it is the part you have the most control over.

Here is how a typical kitchen remodel unfolds, phase by phase, and what tends to slow each phase down.

Kitchen remodel in progress by a Portland-area remodeling contractor

Phase By Phase

01Walkthrough & ScopeWe review the layout, existing conditions, your goals, and budget, then write up the scope
02Design & SelectionsCabinets, countertops, flooring, backsplash, sink, faucet, lighting, and appliances
03OrderingLong-lead items, especially cabinets, are ordered before demolition so the kitchen is not sitting empty
04PermitsNeeded when plumbing, wiring, ventilation, or walls change
05DemolitionOld cabinets, counters, and finishes come out; the room is protected and debris hauled away
06Rough-In & InspectionsPlumbing, electrical, and ventilation are updated, then inspected before walls close
07Walls & FlooringDrywall repair, paint, and flooring, in the order your flooring type requires
08CabinetsBase and wall cabinets installed, leveled, and secured
09CountertopsTemplated after cabinets are set, then fabricated and installed
10Backsplash, Fixtures & AppliancesTile, sink and faucet, lighting, and appliance hookups
11Punch ListFinal adjustments, touch-ups, and a walkthrough with you

Why There Is Often A Gap For Countertops

Stone and quartz countertops are usually measured, or templated, only after the cabinets are installed, because the counters have to fit the cabinets exactly as they sit in your kitchen. The slabs are then cut and finished in a shop before installation. That gap is normal, and it is worth planning around: the sink and dishwasher usually cannot be fully hooked up until the counters are in.

What Slows A Kitchen Remodel Down

  • Late selections. Every decision still open when demolition starts is a chance for the schedule to stop.
  • Back-ordered materials. Cabinets, special-order tile, and appliances can arrive later than promised.
  • Hidden damage. Old leaks under the sink or dishwasher can leave rotted subfloor or framing that has to be repaired.
  • Mid-project changes. Moving an outlet or switching a countertop material after the fact ripples through the schedule.
  • Inspections. Rough-in inspections have to pass before walls are closed, so scheduling them matters.

Living Without A Kitchen

A little setup makes the construction weeks much easier. Most families move the refrigerator, microwave, coffee maker, and a toaster oven or electric burner into a dining room, garage, or basement. A folding table works as a counter. Plan simple meals, keep paper plates on hand, and pick a spot for dishes, like a laundry sink or a bathroom sink with a dish rack nearby.

Completed kitchen remodel with new cabinets and countertops in Tigard, Oregon

How We Keep A Kitchen Remodel On Track

The most effective thing we do is get decisions made and materials ordered before demolition starts, so the kitchen is not torn out while you wait on cabinets. Your written scope and estimate spell out what is included, the allowances, and the exclusions, so there are fewer surprises once work begins. See our kitchen remodeling services, our Tigard kitchen project, and guides on remodeling permits and what belongs in your contract.

Common Questions

How Long Does A Kitchen Remodel Take?

It depends far more on scope than on square footage. Replacing cabinet fronts, counters, and fixtures in the same layout is a much shorter job than gutting the room and moving plumbing, walls, or appliances. Planning and ordering materials often take as long as the construction itself. We give you a schedule with your estimate once the scope and selections are clear.

Can We Live In The House During A Kitchen Remodel?

In most cases, yes. Most families set up a temporary kitchen in another room and keep using the rest of the house. On our Tigard kitchen remodel, the homeowners stayed in the home and the work was sequenced to keep the kitchen usable during the project.

Should I Pick My Appliances Before The Cabinets?

Yes. Cabinet layouts are built around appliance sizes, especially for the refrigerator, range, dishwasher, and any built-in microwave. Choosing appliances early, or at least confirming exact dimensions, prevents gaps and costly changes later.

Does Flooring Go In Before Or After The Cabinets?

It depends on the floor. Floating floors like LVP and laminate are usually installed after the cabinets, because most manufacturers say cabinets should not sit on top of a floating floor. Tile and some hardwood installations can go in before the cabinets. We plan the order around the flooring you choose.

Planning A Kitchen Remodel?

Tell us what you want to change, and we’ll start with a walkthrough and a clear written scope.